Last two weeks were very exhausting. As I was lagging behind my actual milestone planning, I had to work 10-12 hours a day for a hope that I would make it. Until last night when I was informed that my project timeline has been extended to 16 weeks. This gives me a relief and a need break to breathe.
But here’s the update of last two weeks. Okay, now when I see last weeks blog, I don’t think I did many things even though I was working very hard. I definitely need to check for efficiencies in my workflow. However, I did the following:
- Completed M1.2.1 and M1.6 with all the failing tests and they are also approved.
- For M1.7 and M1.2.2, I completed all of the remaining tests and also fixed the issues with failing tests. These are now under review.
- For M1.8, I completed it but many tests are failing and I need to fix them.
- I also got evaluations for pre/post checks and I completed 25% of it in R1.1
I don’t think there is more to discuss. So, yeah, this is my update.